Projects > Industrial Mechanical Projects


Saudi Aramco-Shoaiba
SHY-1 NGL PIPELINE UPGRADE AT PUMP STATION # 06 (LSTK PROJECT)

Detailed design, engineering, procurement of material and equipment, construction/installation of the NGL SHY-1 pumping station including but not limited to all associated civil, piping, electrical, instrumentation, communication and mechanical works.

(2005-2007)
Najran Cement Co.-Najran
NAJRAN CEMENT PLANT

Construction of a new Greenfield cement plant with a capacity of 6,000 tpd OPC/SPRC clinker including a power plant, residential village/colony, all associated equipment, auxiliaries and infrastructure.

(2005-2007)
Saudi Aramco-Juaymah
JUAYMAH GAS PLANT EXPANSION – MECHANICAL TIE-INS

Site survey, site preparation, fencing, supply all materials for civil/ structural and piping tie-in works. Also demolition of existing piping/supports, fabricate and install new piping including Tie-Ins and modifications to existing piping and supports, systems/subsystems/lines Isolation and blinding, hydro-testing and lay up, NDT of welds, painting, coating to all piping and structural steel supports and insulation to all piping, valves and fittings.

(2005-2006)
Saudi Aramco
PLANT WORKS CONSTRUCTION FOR BULK PLANTS

The project requirements includes Additional Capacity Requirements (BI-10-03550) and Two Grades of Gasoline (BI-10-03547) at Miscellaneous Bulk Plants in Central Region. Also includes civil/structural, mechanical/ piping, electrical/instrumentation works.

(2005-2006)
US Army Corps of Engineers
Thumrait Air Base-Sultanate of Oman
TANKER TRANSPORT OFFLOADING FACILITY

Construction of Administration/Filter/Water System Pump/ Buildings, fuel distribution system including offloading stations, sunshades, fuel spill/runoff containment and modifications to POL storage, roads and parking, site electrical including substations and generator, sanitary sewer system, water system including water tanks.

(2005-2006)
Technip/Saudi Aramco-Riyadh
RIYADH REFINERY – DIESEL HYDROTREATER FACILITY

Civil/ buildings, structural/ mechanical/ piping/ equipment erection, heavy lift, electrical/instrumentation, HVAC, sandblasting/painting, cathodic protection, and assistance to final commissioning work.

(2004-2005)
Saudi Aramco-Yanbu
INTEGRATION OF NEW STEAM AND POWER GENERATION AT YANBU NGL PLANT

Civil, Mechanical/Piping/Equipment Erection, heavy lift, structural steel erection, painting/insulation and associated works.

(2003-2004)
Saudi Aramco-Juaymah
FIRE TRAINING CENTER

Construction of a complete Fire Training Center including integrated process complex, integrated structural complex, water & fuel tanks, water treatment plant, substation, control station, external utilities, mechanical, electrical, instrumentation and fire water system.

(2003-2004)
TECHNIP/Saudi Aramco-Haradh
HARADH GAS PLANT

Construction of all utilities and offsite facilities necessary for Haradh Gas Development Program, including all civil works, buildings, piping and mechanical erection, heavy lift, structural steel erection, insulation and painting works.

(2001-2003)
Saudi Aramco-Rabigh Refinery
LPG TRUCK LOADING FACILITY

Civil, Structural, Piping fabrication and erection, equipment erection, electrical/instrumentation, insulation and piping works.

(2001-2003)
Saudi Aramco -Abqaiq Plants
WASTE WATER ENVIRONMENTAL PROTECTION

Installation of new equipment and approximate 23 Km of pipeline to transfer industrial waste water including construction of a 172,884 barrel carbon steel umbrella roof atmospheric surge tank and associated works.

(2000-2002)
TPL Arabia/Saudi Aramco-Abqaiq
POWER PLANT UPGRADE (CO-GENERATION PLANT)

Replacement of the existing Power Plant Combustion Gas Turbine Generators (CGTG 4,5 & 6) with three (3) new CGTG (42 MW) with non-fired Heat Recovery Steam Generators with a new control system.

(2000-2002)
Saudi Aramco-Tabuk & Duba
TABUK & DUBA FIRE FIGHTING PROJECTS

Installation, testing, commissioning of two firewater jockey pumps, firewater storage tank, new firewater piping including all civil, mechanical, electrical and instrumentation works.

(1998-1999)
Al-Jubail Petrochemical Co.
(KEMYA)-Jubail
KEMYA EXPANSION - EARLY CONSTRUCTION WORKS

Relocation/transfer of the existing plant and facilities, and demolition of structures and underground facilities to clear the areas for the construction of a grass root Low Density Polyethylene Plant (LDPE).

(1998-1999)
Arabian Petrochemical Co., (PETROKEMYA)-Jubail
CONSTRUCTION OF 5TH SEA WATER PUMP

All civil, structural, piping pre-fabrication and erection work.

(1996-1997)
U.S. Corps of Engineers
REPLACE DESALT PLANT BOILER

Installation, testing and commissioning of 3 numbers steam generating plant boilers including feed water system, chemical feed systems, pumps, piping, valves control, instrumentation and air system.

(1996-1997)
Saudi Aramco-Riyadh
HYDROSTATIC TANK GAUGING

Hydrostatic tank gauging system at Riyadh Refinery, for 73 tanks including hot tapping installation of 36” long thermo-wells, hydro-testing, NDT, Top End System with provision for addition of tank and radar tank gauging.

(1993-1995)
Al Jomaih Company
CONSTRUCTION OF CAN MAKING FACTORY

Equipment erection, piping, mechanical, electrical and instrumentation works.

(1995)
National Plastic Company
(IBN HAYYAN)/SNAMPROGETTI
PASTE PLANT PROJECT – MECHANICAL WORKS

Site preparation, underground utilities, structural steel, foundations and concrete structures, piping fabrication and erection, equipment erection, tank fabrication and erection, HVAC, sandblasting & painting, pre-commissioning and assistance to commissioning.

(1993-1995)
Saudi Aramco
ZULUF ARABIAN WET CRUDE HANDLING FACILITIES

Civil, structural steel, mechanical, heavy lift erection, piping, electrical, instrumentation, painting, insulation, fire protection, pre-commissioning and assistance to commissioning.

(1992-1994)
Saudi Aramco-Hawiyah
HAWIYAH CENTRAL WATER INJECTION PLANT (HAWIP) PROJECT

Site preparation, civil, structural, mechanical, piping, heavy lift, equipment erection, electrical, instrumentation, HVAC, sandblasting, painting, cathodic protection and assistance to commissioning works including subcontract for up-rating of GE Gas Turbines.

(1992-1993)
MANNESMANN ANLAGENBAU/Saudi Aramco
INCREASE YANBU CRUDE EXPORT CAPACITY PUMP STATIONS & PLANTS (GROUP II P.S. NOS. 5,6,7 & 8) SURGE RELIEF STATIONS.

(1990-1993)
SAUDI ARAMCO
REPLACE HIGH LIFT PUMPS AND SEAWATER DISTRIBUTION SYSTEM

Civil, building, structural, mechanical, piping electrical, instrumentation, sandblasting/painting and commissioning work.

(1991-1993)
Continental Can of Saudi Arabia Limited
CONSTRUCTION OF CAN MANUFACTURING FACTORY

Structural steel fabrication & erection, equipment erection, electrical & instrumentation testing, commissioning and painting works.

(1991-1992)
Saudi Aramco
CONSTRUCTION OF HIGH PRESSURE DI-GLYCALAMINE PLANT (HI-DGA)

Site preparation, civil, structural, mechanical, piping electrical, instrumentation, HVAC, sandblasting, painting, cathodic protection, heavy lift, equipment erection and assistance to commissioning work.

(1990-1991)
Saline Water Conversion Corp. (SWCC)/ TECHNIP
POWER DESALINATION PLANT

Construction of all civil and utility buildings, structural steel erection, mechanical/piping erection, electrical, instrumentation, HVAC, sandblasting/painting, cathodic protection and assistance to commissioning works.

(1998-1990)
Saudi Aramco
CONSTRUCTION OF UGOSP-6 GAS GATHERING FACILITIES

Site preparation, civil, control building, structural steel, mechanical/piping, electrical, instrumentation, HVAC, sandblasting/painting, cathodic protection, heavy lift, equipment erection & assistance to commissioning works.

(1989-1991)
Royal Commission for Jubail & Yanbu
OPERATION & MAINTENANCE FOR SEAWATER COOLING SYSTEM

Operations and maintenance of Seawater Cooling System for primary & secondary Industries at Jubail Industrial City.

(1987-1990)
National Glass Ind. Company / Technologie Progetti Lavori SPA
CONSTRUCTION OF GLASS BOTTLE FACTORY

All civil, structural steel erection, piping erection, electrical and instrumentation, process equipment erection, painting and insulation works

(1989-1990)
SWCC/ Penta Ocean Const. Co. Ltd.
POWER DESALINATION PLANT

Construction of all civil and utility buildings, structural steel erection, mechanical/piping erection, electrical, instrumentation, HVAC, sandblasting/painting, cathodic protection and assistance to commissioning works.

(1985-1989)
Arabian Gulf Oil Company
(AGOC)
CONSTRUCTION OF LUBE OIL BLENDING PLANT

Detail design & engineering, procurement, supply, fabrication, erection commissioning and initial operation and maintenance of the plant.

(1987-1988)
JGC Corporation-Kuwait
(KNPC) KUWAIT REFINERY MODERNIZATION & UPGRADING WORKS

All civil, structural steel, piping, mechanical, electrical, instrumentation, sandblasting/painting, cathodic protection, insulation works.

(1982-1987)
PETROKEMYA
CONSTRUCTION OF POLYSTYRENE PLANT

All civil, structural steel, mechanical, electrical, instrumentation, HVAC, painting, insulation, cathodic protection, pre-commissioning & assistance to final commissioning.

(1986-1987)
SWCC/ Penta Ocean Const. Co. Ltd.
MAKKAH-TAIF DESALINATION PLANT

All civil and utility buildings, structural steel erection, mechanical/piping erection, electrical, instrumentation, HVAC, sandblasting/painting, cathodic protection and assistance to commissioning works.

(1984-1987)
Mitsubishi Corporation
LIMESTONE CRUSHING PLANT & TRANSPORT-ATION SYSTEM, AL-JADIDAH QUARRY DEV. PROJECT

All civil, structural steel, piping, mechanical, electrical, instrumentation, sandblasting/ painting, cathodic protection, insulation & commissioning work.

(1986-1987)
Al Jubail Petrochemical Co. (KEMYA)
CONSTRUCTION SERVICE AND MODIFICATION OF LLDPE PLANT

All civil, structural steel, piping, mechanical, electrical, instrumentation, sandblasting/ painting, cathodic protection, insulation works.

(1985-1990)
Saudi Aramco
PUMP STATIONS (PS 5-8)

Modification Segment of the East / West Crude Pipeline Capacity

(1986)
Saudi Aramco
RAS TANURA REFINERY MODERNIZATION

Civil, utility, buildings, structural, mechanical piping, electrical, HVAC and instrumentation works.

(1983-1986)
Royal Commission
SANITARY WASTE WATER TREATMENT PLANT NO. 9, STAGE2

Civil, buildings, structural steel, mechanical piping, electrical, instrumentation, HVAC, commissioning & initial operation and maintenance works.

(1982-1986)